Surfside Beach Renourishment — 2026 Status

Last updated: July 22, 2026

In progress — started early July 2026. Segment: Reach 3. Timeline: Early July 2026 – late August 2026.

Surfside Beach is part of Reach 3, the project’s final phase, and sand placement is underway. Under a revised mid-July plan, the work zone runs from the Garden City line north to just before the Third Avenue South swash; the stretch from Third Avenue South to Fifth Avenue North has already reached its target elevation and gets no more sand. As of mid-July 2026, crews are working from 14th Avenue South to Sixth Avenue South, after which they move to the Fifth Avenue North area and continue toward Myrtle Beach State Park. Work is expected to continue into late August 2026.